TCN LINESMEN COMMENCE REPAIR WORKS ON FAULTY UGWUAJI – APIR LINE
Following the blackout recorded in some parts of the country earlier in the week, the Transmission Company of Nigeria, TCN, dispatched a team of linesmen to locate the fault and thereafter, effect repairs in order to restore power to the affected areas.
Accordingly, the team of linesmen were able to discover the fault identified as the Ugwuaji–Apir 330kV Double Circuit transmission line, at about 1700hrs on Tuesday evening, in the Igumale area of Benue State.
A statement issued by the General Manager Public Affairs Division of TCN Ndidi Mbah Mrs, disclosed that "The fault area of the transmission line, which measures about one span, was found to be a snapped 330kV transmission line located in the swampy forest of Igumale. Having made the discovery earlier in the evening of today (Tuesday 23 October), arrangements are already ongoing to mobilise equipment and materials that would be moved to the site of the incident to enable TCN commence repair works.
"Due to the difficult and swampy nature of the terrain, TCN would require to move a bulldozer and other materials for the repair works from Enugu Regional office of TCN to the site of the incident. A Hiab vehicle would also be moved to Igumale to help TCN properly tension the transmission line." The statement read.
"Recall that on the Monday, 21st of October, 2024, the 215KM Uguwaji – Apir Double Circuit transmission line tripped due to fault, causing forced power outage across the North East and North West and parts of the North Central regions of the nation. Previous attempts by two dispatched teams to locate the cause of the forced outage were unsuccessful until this evening.
"TCN is committed to promptly addressing the situation and is urgently organizing the necessary materials for the repair work. We appreciate the patience of the government and electricity customers in the affected states. Please bear with us." The statement concluded.