SLEAZE IN NIGER DELTA MINISTRY RESPONSIBLE FOR POOR PERFORMANCE
CONTRACT VIOLATION; BANE OF POOR PERFORMANCE BY THE NIGER DELTA MINISTRY
The factors responsible for the stunted growth of the Niger
Delta Ministry, has been traced to the violation of contract award process,
sleaze and other issues.
This was the findings of a report by a Ministerial Technical
Audit Committee on the Contracts awarded by the Ministry between 2009 and 2015.
Recall, the Niger Delta Ministry was a creation by the
government of late President Umaru Musa Yar’Adua in 2008 to oversee the
region’s development and improvement.
Most of the contracts awarded in the oil-rich region according
to the Committee’s report, has had no impact on the people. It also revealed
that only N427 billion, representing 60 per cent out of N700 billion, budgeted
for the Ministry during the period, was disbursed while projects worth over
N273 billion for which had been paid for cannot be accounted for, says the
report.
Created as a special purpose vehicle to facilitate the
development of the region, the Niger Delta Ministry is reported not to have
impacted purposefully for the people of the region with the following states being
the beneficiaries; they are Abia, Akwa Ibom, Bayelsa, Cross River, Delta, Edo,
Imo, Ondo and Rivers.
The committee which was set up this year by the Honourable
Minister of the Niger Delta Ministry, its task is to evaluate and prioritize
the projects embarked upon by the Ministry in the nine Niger Delta states based
on the availability of funds and overall impact on the living conditions of the
benefitting communities.
The committee’s report has however, recommended the
termination of six projects while urging the refund of the amount collected on
two others.
“All projects were to achieve the objective of enhancing
socio-economic activities, human capital development and environmental
protection of the region”.
“Sadly, very insignificant numbers of projects have reached
practical completion to provide the sense of belonging expected by Niger
Deltans across board”, the committee stated in its report.
“About 80% of the projects are either on-going, abandoned
after payments, total abdication or refusal to deliver as in the case of Youth
Capacity Building Programmes”.
“The well intended Federal Government intervention programme
in the Niger Delta Region was poorly implemented six years after flag-off with
serious consequences,” the report stated.
The total cost of projects the committee said it found out within
the period was N700,538,741,691.30 excluding services (security, rent and
facility management), adding that N446,421,385,864.41 was certified for payment
but N423,172,256,347.84 was paid.
“In other words, between 2009 and 2015, about 60% of
contracts awarded were paid, but approximately 40% of work was practically
achieved”.
Juxtaposing its finding from the project sites against fact
retrieved from available documents domiciled in the departments that supervised
the projects, the committee observed that ‘there was violation of contract
award process”.
The way billions of naira are mentioned in construction
projects value in the Ministry of Niger Delta Affairs has become so banal that
very soon, it is believed that they are likely to escalate to trillions of naira,
even though the values do not appear realistic vis-Ã -vis the value added to the
region through such contracts”, it stated.
Right from the cycle of procurement planning to contract
award, the committee claimed it noticed “inconsistencies with the provisions of
vital aspects of the Procurement Act”.
Accordingly, prominent amongst other issues of violation, the
committee observed “indiscriminate award of contract by initiating and
benefiting departments without the leading and guiding role of the procurement
department”.
“Awards never took cognizance of availability of funds and annual
appropriation provisions, the structure and content of some contract agreements
were loose for checks and balances, indeed hardly protected the interest of the
ministry in case of disputes.”
On delivery and capacity, the Ministerial Technical Audit Committee
said the imminent picture of abandoned and uncompleted projects was as
disturbing as the retinue of projects that extremely exceeded the dates of
completion.
“This manifestly, emanated from inconsistency in government
annual budgetary provision and lack of capacity to deliver especially where
funds released do not correspond with performance”.
“Most contracts were awarded with specific dates of
completion but were not captured in subsequent appropriations. This further
exacerbated contractors’ poor performance and inability to achieve project
objectives. Consequently, no capital project was completed within the
stipulated time frame”, it said.
No comments:
Drop Comment