FG TASK JULIUS BERGER ON TIMELY PROJECT DELIVERY .... Appraises Performance Of All Ongoing Projects Awarded To Construction Firm

"Be open to a mutually agreed modality for milestone execution and funding of the projects at reviewed rates as may be agreed upon and approved by the Federal Executive Council." Umahi Urges, Julius Berger, contractors 


As part of measures by the Renewed Hope administration to mitigate the sufferings of road users at this moment of economic challenges, the Federal Ministry of Works has opened a decisive discussion with Julius Berger Nigeria Plc on all the inherited and new projects handled by them with a view to appraising their performance and take decisions on funding and milestones completion of all such awarded projects.

This is in keeping with the directive of the Federal Executive Council with respect to all inherited and new projects being  handled by a number of multi national companies that have experienced delays due to issues of price differentials or poor funding, 

This was the outcome of a crucial meeting organized by the Ministry with the management of Julius Berger Plc held at the Ministry's Headquarters, Mabushi-Abuja on 7th August 2024.

Speaking on the resolutions reached  during the meeting, the Minister of Works, Engr. David Umahi, reiterated the firmness of the Ministry on issues of price control, commitment of contractors to project execution, value for money, and uniform  pricing location by location. 

The decried the unacceptable conditions of some of the inherited and new projects of all ongoing federal roads awarded to Julius Berger Plc, which are within the economic  corridor of the nation and which were being delayed due to issues of price differentials or lack of effective funding. 

Umahi, at the meeting, listed the projects affected to include: the 82km by 2 dualization of section of Abuja-Kaduna- Zaria-Kano Highway currently handled by Julius Berger; Phase 2 of the Lagos-Ibadan expressway, whose pavement elements  had been changed from asphalt to concrete; Section 2A bypass at the 2nd Niger Bridge whose pavement element was changed to concrete; the Bodo-Bonny road funded by NLNG Tax Credit; the underdeck structural works at 3rd Mainland bridge, Iddo bridge and Carter Bridge.

The Minister urged the contractor to be open to a mutually agreed modality for milestone execution and funding of the projects at reviewed rates as may be agreed upon and approved by the Federal Executive Council. 

"Our job is to develop this mechanism based on FEC directives, and engage with the Honourable Minister of Finance and Coordinating Minister of the Economy, and finally we take our recommendations back to Mr. President, and of course FEC for consideration." 

Speaking on the section of the Abuja-Kaduna- Zaria-Kano road project that was agreed to be handled by Julius Berger Plc, Engr Umahi commended the quality of work being done but directed that the contractor sticks to one carriageway at a time within the scope and conclude their works. 

He further directed the contractor to, within three weeks, fill the two carriageways with stone base and level it to alleviate the sufferings of road users. 

He said; "We agreed that this project, within their own corridor, will last for 14 months. Project execution should be deployed in four sections, and we will be paying Berger ₦20 billion every month to get the job completed".

Addressing the issue of the Phase 2 of the Lagos-Ibadan Expressway, Engr Umahi disclosed that the Ministry had no choice  but to determine the contract and ask the Bureau of Public Procurement for a No Objection for selective tendering. 

"We changed the elements of the pavement from asphalt to concrete, and the total cost we came up with, based on prevailing cost is ₦153 billion. But they are offering ₦258 billion. Since we have been on this since September 2023, we have no choice but to determine this contract and then, we asked BPP for No Objection for selective tendering, whereby we will be sending our own advice of ₦153 billion to BPP, and we send their own of ₦258 billion to BPP. Thereafter, we will invite other contractors to also bid. This we will conclude within the next one month so that we can get that job concluded."

On the Second Niger Bridge Bypass handled by Julius Berger Plc, the Honourable Minister of Works said; "One of the bypasses, which is 17.27 kilometers by two on asphalt was awarded to Julius Berger. We changed the pavement elements to concrete and the cost that we came up with was ₦133 billion. Berger almost gave us more than twice our cost, which is ₦279 billion. We have disagreed with this cost at the time of negotiation since September 2023. We have also decided to get the project back to BPP and invite more contractors to bid because, this is public fund".

Umahi while speaking on the Bodo-Bonny project being funded by NLNG Tax Credit, expressed concerns that Julius Berger Plc, that though, had mobilized back to site after additional cost of N80 billon was approved for the work, disclosed that reports available  to him showed that their pace of work was slow. 

He further expressed his worries that they came up with a longer timeline of 16 months within which to deliver the project as against the December 2024 deadline proposed by the Ministry.

"We agreed on an additional cost of ₦80 billion, which will bring the project to about ₦280 billion fixed and non-varying with the unit rates agreed, and we agreed that this project will not increase in cost beyond ₦280 billion". 

He urged the contractor to shift ground to a shorter timeline for the sake of the people. 

Concerning the underdeck structural works at 3rd Mainland Bridge, Iddo bridge, Carter Bridge in Lagos State, he commended the contractor for doing a fantastic work. 

He said; "We have no problems on pricing. We have paid 30% due to the intervention of Mr. President. They are working, and we have directed that each time they put a certificate and we still have funds, we will pay within seven days because this job they are doing is very critical. For 53 years, those bridges were constructed, no maintenance which has made its deterioration so horrible and frightening. Right now, we have closed the 3rd Mainland Bridge against big trucks.

On the Odukpani road project in Cross River State, the Minister disclosed that, "We have got approval from Federal Executive Council to increase their project by ₦36 billion, thereby raising the project cost from ₦54 billion to ₦90 billion. This was just approved a few days ago. We want to know their response on that. Yes, we have agreed to change the pavement to concrete, and our position is that they have to engage on one carriageway when we agree on this.

"It is when we agree on all these ones where we do not have complete funding that we can enter into the second phase of what FEC directed, and that is to discuss the mechanism". The Minister stated 

In his remarks, the Permanent Secretary of the Ministry, Yakubu Adam Kofarmata, PhD, stated that some of the ongoing road projects handled by contractors required emergency works to alleviate the sufferings of road users and assured that all the supervising engineers would be on their toes to ensure that the Ministry's  policy of Operation Free our Roads was carried out by all the contractors handling  federal government roads nationwide. 

On the section of Abuja-Kaduna-Zaria-Kano Highway handled by Julius Berger Plc, He said, "we have requested this emergency work due to the flow of information and the requests that we have been getting from Nigerians plying Abuja to Kano, more especially Abuja to Kaduna road, where a number of big craters have been created on that road".

This was contained in a statement issued and signed by Ori Uchenna Orji, Special Adviser on Media and Publicity to the Minister of Works and made available to journalists in Abuja.