Power Push: TCN, AfDB Roll Out Fresh Compensation for Alaoji–Onitsha Grid Upgrade


"The Alaoji–Onitsha project involves upgrading a 138-kilometre, 330kV single circuit line to a more robust 330kV double circuit quad conductor system—an enhancement expected to significantly improve electricity transmission capacity and grid reliability across the region" TCN 


The Transmission Company of Nigeria (TCN), in partnership with the African Development Bank (AfDB), has commenced the second phase of compensation for communities affected by the Alaoji–Onitsha Transmission Line Project, reinforcing efforts to modernise Nigeria’s power infrastructure while cushioning social impact.

The latest compensation exercise, carried out between May 12 and 13, 2026, targets Project Affected Persons (PAPs) in Abia and Imo States, with the official flag-off held in Imo. This phase specifically focuses on farmers whose crops fall within the transmission corridor, following an earlier round that compensated owners of impacted structures.

The Alaoji–Onitsha project involves upgrading a 138-kilometre, 330kV single circuit line to a more robust 330kV double circuit quad conductor system—an enhancement expected to significantly improve electricity transmission capacity and grid reliability across the region.

Speaking through the Assistant General Manager and Project Manager for AfDB-backed projects, Engr. Omobola Odusoga-Bola, the Managing Director/CEO of TCN, Sule Ahmed Abdulaziz, praised President Bola Ahmed Tinubu for prioritising the project and ensuring prompt compensation for affected communities.

Beyond compensation, TCN is also implementing a Livelihood Restoration Programme aimed at sustaining economic activities disrupted by the project. The initiative has identified 210 small business operators within the transmission corridor, while 64 beneficiaries from 32 communities are set to receive vocational training and startup support in trades such as tailoring, shoemaking, catering, ICT, auto mechanics, and electrical installations.

Project Consultant and Managing Director of PGM Nigeria Limited, Bassey Uzodimma, described the intervention as a model of responsible infrastructure delivery, urging community leaders to ensure transparency and maximise long-term benefits for beneficiaries.

The compensation and livelihood support efforts underscore a broader attempt by TCN and its partners to balance infrastructure expansion with social responsibility, as Nigeria pushes to strengthen its national grid and drive economic growth.